The Civil Engineering and Development
Department HKSAR has appointed MateriaLab Consultants
Limited (MCL) to undertake the Environmental Team services for the Project and implement
the EM&A works.
ii.
This Monthly EM&A report presents the
environmental monitoring and audit works for the period between 1 October and 31
October 2020. As informed by the Contractor, major activities in the reporting month
were:
Utility laying
Construction of road base and
road pavement
Landscape works – irrigation
systems, tree and shrub planting
Laying Cable and Construction
for Road Lighting
Breaches of the Action and Limit Levels
iii. Three Action Level exceedance for 24-hr TSP
were recorded. An exceedance was recorded at KTD2c on 14 October 2020 and two exceedance
was recorded at KER1 and KTD2c on 24 October 2020. No Action / Limit Level
exceedance was recorded for 24-hr TSP at KTD1 in the reporting month.
iv. A Limit Level exceedance for construction
noise was recorded. Exceedance was recorded at KTD1 on 21 October 2020. No
Action / Limit Level exceedance was recorded for construction noise at KTD2c
and KER1 in the reporting month.
Complaint, Notification of Summons and Successful Prosecution
v. No environmental complaint, notification of
summons and successful prosecution were received in the reporting month.
Reporting Changes
vi. There was no reporting change in the
reporting month.
Future Key Issues
vii. The key issues to be considered in the
coming reporting month include:
Potential environmental
impacts arising from the above construction activities are mainly associated
with construction dust, construction noise, water quality, waste management and
landscape and visual impacts.